Read the planner
Each row shows a person’s name, job role, and their allocated and available hours for the dates in view, for example 5h / 37.5h. The total turns red when they’re allocated beyond what they have. In Days columns, each working day is a small square:- The fill shows how much of the day is Allocated.
- Over is red: more is allocated than the person has that day.
- Off but allocated has a red border: work is allocated on a day the person is away.
- Time off shows as an icon, such as Holiday, Sick, Parental leave, Bank holiday or Office closed. A Part day off is frosted across the top.
- Days the person doesn’t work are faint.
Allocate hours
To allocate someone to a project, do one of these:- Select New allocation at the top of Workload, then choose who and the project in the dialog.
- Click an empty day, or drag across days on a person’s row.
- Select + next to their name.
- Click + in the day tile.
- Choose who in Person or role and the Project. Projects that are in progress come first, then those not started, then the backlog. Done and cancelled projects are hidden: select Show N done or cancelled projects at the bottom of the list to see them, or search for one.
- Set the Start date and End date, or tick No end date for ongoing work.
- In Measured as, choose Per day, Per week, Per month or Total, then enter the hours. Per day has Full day and Half day shortcuts. Total needs an end date.
- Choose a Status: Confirmed, or Tentative for work that’s pencilled in. Tentative allocations are dashed, and their hours don’t use up free time or count as overtime until they’re confirmed.
- Select Save.
Plan ahead with job roles
You can allocate hours to a job role before you know who’ll do the work, for example “Project A needs a designer for 4h a day”.- Start an allocation as usual, or in Group by Job role select + on the role’s header.
- In Person or role, choose a role under Job roles: choose someone later.
- Fill in the project, dates and hours, and select Save.
- Drag the allocation onto their row, or
- Open the allocation and choose them in Person or role. People with that role are listed first, with their free hours.
Change an allocation
- Move an allocation by dragging its bar, including onto another person’s row. Cards due in that period move with it.
- Resize it by dragging its start or end.
- Edit it by clicking the bar. Delete is in the dialog.
- With a bar focused, Alt + arrow keys move it and Alt + Shift + arrow keys change its end.
Change the view
- Pick the dates from the range button, or use Today and the arrows. Presets run from This week to Next quarter.
- Filter by Project or Person, or search people by name.
- Layout sets:
- Show in: Hours or Days.
- Group by: Person, Job role or Project.
- Columns: Days or Weeks.
- Hide weekends: leaves out weekend days nobody works.
Group by Job role
People are grouped under their job role, with each group’s combined allocated and available hours per day or week. One person’s free time absorbs another’s overtime, so you can see whether a role as a whole has room. Every job role is listed, including ones nobody has yet, so you can plan for a role you’re still hiring for (roles nobody has are left out while you search or filter). Select + on a role’s header to allocate hours to it.Group by Project
Each project gets a row comparing the hours allocated on it with the hours it needs, marked Short, Covered or More than needed. Only confirmed allocations count. A project’s needed hours come from its budgets, one in charge on any day:- On the days a recurring budget runs, each period’s hours are spread over that period’s working days (a period the budget only partly covers gets a share of the hours, spread over the days it runs).
- On the project’s other days between its start and due dates, its time budget is spread over the working days no recurring budget covers.
What needs you
The sidebar lists what needs a decision in the dates you’re viewing:- Needs someone: budget hours nobody is allocated to yet. Drag them onto a person to allocate them.
- Off but allocated: work allocated while someone is away. Select Suggest someone to see who could take it, or move it to the person’s next working days.
- Over: weeks where someone is allocated beyond their capacity. Suggest someone else, or push the allocation a week.
- Outside project dates: allocations that start before or run past their project’s dates. Fit to dates proposes moves that fit.
- Who’s free: people with the most free time.
Time off
Add time off for someone from the Time off tab when you start an allocation: choose the dates, a reason (Holiday, Sick or Off), and for a single day, whether it’s the morning or afternoon. If your workspace is connected to CharlieHR, approved leave, working weeks, offices and company holidays sync from there instead. Synced time off can only be changed in CharlieHR, and the planner shows when it last synced. Admins can sync again from the planner. Who sees why someone is off is a workspace setting: admins and the person, or everyone. Others see Away.Settings
Workspace owners and admins set up what the planner works from in Settings > Resourcing, or from the ⋯ menu in Workload:- Working time: the default working week and day length, locations with their public holidays, office closures, and who sees why someone is off.
- Roles and rates: job roles with their rates, rules that give people a role from their HR job title, and each person’s role and own rate. Admins can also change someone’s role from their row in the planner.
- Time tracking: billable defaults, privacy and time categories.